Clarification on Non-notifiable and Notifiable projects
1 November 2006
Demolition is treated the same as all other construction work, notifiable only if the work lasts longer than 30 days or 500 person days of construction work. However regulation 29 requires a written plan to be prepared before work starts detailing the arrangements for all demolition. A file is only required for notifiable jobs. Regulation 17[3] b refers to notifiable jobs and is therefore not applicable. For projects where there is an existing file and some non notifiable work is done and there...