Skip to main content

Health and Safety File

CDM (Jersey) Knowledge Base

CDM (Jersey) 2016 Regulations
Please note this topic relates to the CDM (Jersey) 2016 Regulations. If you are looking for the CDM 2015 (Great Britain) Regulations, please see the CDM (GB) Knowledge Base

The health and safety file is information regarding the main design decisions, any residual hazards etc. for a construction project. The size of the file may vary dependant on if the project was a major or minor works.

The health and safety file should contain the information needed to allow future construction work, including cleaning, maintenance, alterations refurbishment and demolition to be carried out safely. The scope, structure and format of the file should be agreed between the client and the Designer at the start of the project.

What is the Health and Safety File?

The health and safety file is defined as a file appropriate to the characteristics of the project, containing relevant health and safety information to be taken into account during any subsequent project.

The file must contain information about the current project that is likely to be needed to ensure health and safety during any subsequent work such as maintenance, cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:

  1. A brief description of the work carried out;
  2. Any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (e.g. surveys or other information concerning asbestos or contaminated land);
  3. Key structural principles (e.g. bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
  4. Hazardous materials used (e.g. lead paints and special coatings);
  5. Information regarding the removal or dismantling of installed plant and equipment (e.g. any special arrangements for lifting such equipment);
  6. Health and safety information about equipment provided for cleaning or maintaining the structure;
  7. The nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
  8. Information and as-built drawings of the building, its plant and equipment (e.g. the means of safe access to and from service voids and fire doors).

There should be enough detail to allow the likely risks to be identified and addressed by those carrying out the work and be proportionate to those risks. The file should not include things that will be of no help when planning future construction work such as pre-construction information, the construction phase plan, contractual documents, safety method statements etc. Information must be in a convenient form, clear, concise and easily understandable.

What Must Duty Holders Do In Regard To The Health & Safety File?

The Client

The client must ensure that the health and safety project coordinator prepares the health and safety file for a project. As the project progresses, the client must ensure that the health and safety project coordinator regularly updates, reviews and revises the health and safety file to take account of the work and any changes that have occurred. The client should be aware that if the health and safety project coordinator appointment finishes before the end of the project, the health and safety project coordinator must pass the health and safety file to the principal contractor, who then must take on the responsibility for the file.

Once the project is finished, the client should expect the health and safety project coordinator to pass them the health and safety file. In cases where the health and safety project coordinator has left the project before it finishes, it will be for the principal contractor to pass the file to the client. The client must then retain the file and ensure it is available to anyone who may need it for as long as it is relevant – normally the lifetime of the building - to enable them to comply with health and safety requirements during any subsequent project. It can be kept electronically, on paper, on film, or any other durable form.

If a client disposes of their interest in the building, they must provide the file to the individual or organisation who takes on the client duties and ensure that the new client is aware of the nature and purpose of the file. If they sell part of a building, any relevant information in the file must be passed or copied to the new owner. If the client leases out all or part of the building, arrangements should be made for the file to be made available to leaseholders. If the leaseholder acts as a client for a future construction project, the leaseholder and the original client must arrange for the file to be made available to the new health and safety project coordinator.

The Designer

Where it is not possible to eliminate health and safety risks when preparing or modifying designs, designers must ensure appropriate information is included in the health and safety file about the reasonably practicable steps they have taken to reduce or control those risks. This will involve liaising with:

  1. The health and safety project coordinator in helping them carry out their duty to prepare, update, review and revise the health and safety file. This should continue for as long as the health and safety project coordinator’s appointment on the project lasts; or
  2. The principal contractor where design work is carried out after the health and safety project coordinator’s appointment has finished and where changes need to be made to the health and safety file. In these circumstances, it will be the principal contractor’s duty to make those changes, but the designer must ensure that the principal contractor has the appropriate information to update the file.

This information should be provided to the health and safety project coordinator and principal contractor as early as possible before the designer’s work ends on the project.

Health and Safety Project Coordinator

The health and safety project coordinator is responsible for preparing the health and safety file. They are accountable to the client and should liaise closely to agree the structure and content of the file as soon as practicable after appointment. In preparing the file, the health and safety project coordinator should expect the client to provide any health and safety file information that may exist from an earlier project.

The health and safety project coordinator must also cooperate with the rest of the project team and should expect their cooperation in return. Cooperation with the principal contractor is particularly important in agreeing the structure and content of the information included in the file. Liaison with designers and other contractors is also important. They may hold information that is useful health and safety project coordinator, in cooperation with other members of the project team must also ensure that the file is appropriately updated, reviewed and revised as necessary to ensure it takes account of any changes that occur as the project progresses.

The health and safety project coordinator must pass the updated file to the client at the end of the project. In doing this, they should ensure the client understands the structure and content of the file and its significance for any subsequent project. If the health and safety project coordinator appointment finishes before the end of the project, they must pass the file to the principal contractor who must then take on responsibility for it. In doing this, the health and safety project coordinator should ensure the principal contractor is aware of any outstanding issues that may need to be taken into account when reviewing, updating and revising the file. For more information see health and safety project coordinator.

The Principal Contractor

For the duration of the health and safety project coordinator appointment, the principal contractor plays a secondary role in ensuring the health and safety file is fit for purpose. They must provide the health and safety project coordinator with any relevant information that needs to be included in the health and safety file.

Where the health and safety project coordinator appointment finishes before the end of the project, the principal contractor must take on responsibility for ensuring that the file is reviewed, updated and revised for the remainder of the project.

At the end of the project the principal contractor must pass the file to the client. In doing this, they should ensure the client understands the structure and content of the file and its significance for any subsequent project.

The Contractor

The contractor has no specific duties placed on them in relation to the health and safety file.

What is NOT required in the file

The file does not need to include things that will be of no help when planning construction work, for example

  • Pre-construction information that is no longer relevant, or the construction phase plan
  • Construction phase risk assessments, method statements and COSHH assessments
  • Details about the operation and maintenance of the completed structure, although references should be provided to O & M Manuals
  • Construction phase accident statistics
  • Names and addresses of contractors and designers involved in the project
  • Contractual documents
  • Information about structures or parts of structures that have been demolished-unless there are any implications for remaining or future structures, eg voids
  • Information contained in other documents, but relevant cross references should be included

File Format

The regulations do not specify a file format as this may vary according to the project circumstances. Clients are expected to know how completed projects are to be managed from a health & safety perspective and should therefore discuss this issue with the appointed health and safety project coordinator at the start of any project. Clients should make their needs clear regarding scope, structure, format and media required with suitable backup arrangements. The overriding concern should be to make the access of information about health & safety from the file easy to achieve by anyone with a justifiable need to receive that information.

The CDM ToolKit™ has been developed for this specific purpose. In use in organisations throughout the UK since 1995 (and updated inline with the latest regulations), the software solution is available with internet access to the health & safety file. This allows any authorised personnel to access health & safety information about any published file via the internet and on demand. This allows all parties involved to monitor and collate the information required as the project progresses on line and at minimal cost to all the parties concerned.