Question | Answer | |
---|---|---|
Q1 | Is the construction work scheduled to last at least 30 working days? | Yes |
Q2 | Will there be more than 20 workers working simultaneously at any point? | No |
Q3 | Will the construction work exceed 500 person days? | Yes |
This questionnaire is available in CDM ToolKit CS™, where the details are recorded for individual projects And can be reported on.