Is there a monetary value to which CDM applies?

e.g. some of my co-workers insist that anything £25,000 or less will not attract the CDM Regulations.

#73 Ai Solutions posted on 24 September 2004, 16:45

The question above was originally posed via our Ask A Guru feature and this response from 2004 was by either Dave Carr or Michael Stokes.

The CDM regulations make no reference to values of work, only time periods / numbers of personnel working on site (except of course in relation to demolition, where the regulations apply whatever).

In practice, there must be a monetary value connected with this time/personnel criteria although whether this is £25,000 will be dependant upon the individual circumstances. It could not be justified to seek to ignore CDM just because the value of works are less than £25,000.